Case study

Branfil Primary School

Overview

Client Name: London Borough of Havering

Project Value: £92,000

Project Duration: 6 weeks

Hollmark Ltd successfully delivered a full refurbishment and reconfiguration of the pupil toilet facilities at Branfil Primary School. The project was undertaken during the school shutdown period, ensuring the upgraded facilities were fully operational on the return of staff and pupils.

Scope of works

  • Complete strip-out of existing facilities

  • New boys' and girls' toilet areas

  • New staff WC and storage space

  • Partitions and door alterations

  • New sanitaryware, cubicles and wash troughs

  • Drainage and plumbing modifications

  • Hygienic wall cladding and vinyl flooring

  • Electrical, lighting and ceiling upgrades

  • Full decoration package

Onsite challenges

Delivering the full refurbishment within a restricted half-term programme required detailed planning, early procurement and close coordination between trades.

Existing services and drainage infrastructure required alteration while maintaining programme certainty and quality standards.

Project Outcome

The completed facilities provide a bright, modern and durable environment for pupils and staff. Improved layouts, accessibility enhancements and robust finishes ensure long-term performance while creating a significantly improved user experience.