Case study
Client Name: East London NHS Foundation Trust
Project value: £18,000
Project Duration: 2 Weeks
Refurbishment of the existing patient shower / toilet room.
New anti-ligature toilet on sensor
New anti-ligature hand wash basin on sensors
New anti-ligature shower head spout with sensor controls
New anti-ligature access panels
Anti-pick mastic
Hygienic Cladding to form smooth walls.
Anti-ligature lighting fittings
Safety and Security requirements to ensure the security and safety of service users can lead to restrictions and delays which can be very time consuming and can mean a lot of downtime.
Sensitivity to service users: must be mindful at all times of service users’ privacy and confidentiality.
To priorities safety and security measures to ensure the safety of service users, staff and construction workers.